
The PMP exam includes math questions. Know these formulas cold.
Earned Value:
CV = EV − AC (Cost Variance)
SV = EV − PV (Schedule Variance)
CPI = EV/AC (Cost Performance Index)
SPI = EV/PV (Schedule Performance Index)
EAC = BAC/CPI (Estimate at Completion)
ETC = EAC − AC (Estimate to Complete)
TCPI = (BAC−EV)/(BAC−AC) (To Complete Performance Index)
Communication channels:
n(n−1)/2 where n = stakeholders
PERT (3-point estimate):
(O + 4M + P) / 6 (weighted average)
Standard Deviation = (P − O) / 6
Float:
Total Float = LS − ES = LF − EF
Present Value:
PV = FV / (1+r)^n
Point of Total Assumption (FPIF contracts):
PTA = [(Ceiling Price − Target Price)/Buyer's Share Ratio] + Target Cost
Contract incentive fee (CPIF):
Actual fee = Target fee + [(Target cost − Actual cost) × Share ratio]
Reference:
TaskLoco™ — The Sticky Note GOAT